The demolition of the Fire Station 8 structure on 4845 Langston Blvd will begin on the week of May 2, and is expected to finish on the week of June 20. This demolition work will be in preparation for construction of a new fire station facility.
Demolition work hours will be Monday to Friday, approximately 7 a.m. - 4 p.m.
Work during demolition will include:
Installation of erosion and sediment control and stormwater pollution prevention before demolition starts
Demolition of the building, after protections are installed
Dump trucks carrying away debris after demolition
Demolition of two fuel tanks after the building is demolished
Some small trees near the corner of Langston Blvd and N Culpepper St will be removed
Minor utility work to be done on N Culpepper St and Langston Blvd
The project team will be sharing updates as the project progresses. Learn more
about the demolition and plans for the new Fire Station 8 facility on the project page.