Rosslyn/Custis Trail Detours to Begin Next Week
0
Votes

Rosslyn/Custis Trail Detours to Begin Next Week

Custis Trail users — in the vicinity of N. Lynn Street and Lee Highway — will begin experiencing detours next week. Arlington County, along with Virginia Department of Transportation (VDOT) and Dominion Virginia Power, will be performing utility work; part of the Lynn Street Esplanade and Custis Trail Improvements project. Trail users are advised to be aware of changing detour signs as project utility work progresses.

Below is a list of work dates and specific detour locations. Work dates are estimated and may vary:

Phase I:

Street work to be completed March 11

  • No trail detour

Phase II (red dotted line):

Detour east of N. Lynn Street March 8-April 17

  • Trail will be rerouted onto adjacent paved public driveway. Detour area will have signs and temporary trailer mounted lighting.

  • Detour area has a steeper grade than current trail. Bicyclists are asked to dismount before entering and exiting the detour zone.

Phase III (yellow dotted line):

Detour at northeast corner of Trail Crossing at N. Lynn Street April 18 - May 8

  • Trail will be rerouted around work area at northeast corner at N. Lynn Street; crossing will be shifted north. Detour area will have signs and temporary trailer mounted lighting.

Phase IV (solid yellow line):

Detour west of N. Lynn Street May 9 – June 6

  • Trail will be rerouted to the south (Gateway Park) side of Lee Highway between N. Lynn Street and N. Fort Myer Drive.

  • The detour route is narrower than current trail. Bicyclists are asked to slow down or dismount when pedestrians are near.